Construction Updates


Restoration Project Update (as of June 2019)

For current construction updates and restoration information resources, please visit the Portland Parks & Recreation website

Keller Fountain: Project Update

Fountain is currently estimated to be turned on the week of July 8. Updates will follow if this target date is not possible.  Remaining work includes:
•    Wall and fountain lighting replacement (partially complete)
•    Feature mast pole lights installation (poles installed; lights to be mounted)
•    Catch basin grates replacements
•    Concrete fountain and pavement joint sealing and patching
•    Pressure washing (Added new work utilizing contingency funds)
•    Replanting lower fountain beds (Added new work utilizing contingency funds – work by PP&R crews)
•    Punch list work

 

Lovejoy Fountain Plaza: Project Update

Fountain is currently estimated to be turned on the week of July 1. Updates will follow if this target date is not possible. Remaining work includes:
•    Wall and fountain lighting replacement (partially complete)
•    Fountain pump electrical service reconfiguration (nearly complete)
•    Trench drain grates replacements, utility cover replacements (nearly complete).
•    Pavement joint sealing and patching
•    Pressure washing – completed (Added new work utilizing contingency funds)
•    Punchlist work

 

Source Fountain

Fountain is currently estimated to be turned on the week of June 3. Updates will follow if this target date is not possible. Remaining work includes:
•    Trench drain grates replacements
•    Concrete pavement joint sealing
•    Pressure washing – completed (Added new work utilizing contingency funds)
•    Punchlist work

 

Pettygrove Fountain Park

Fountain is currently estimated to be turned on the week of July 8. Updates will follow if this target date is not possible. Remaining work includes:
•    Catch basin and trench drain grates replacements
•    Asphalt pavement full path width overlay currently scheduled for week of June 17, weather dependent. (Added new work utilizing contingency funds – About half of the park area where the storm pipe work occurred)
•    Punch list work

For more information contact:
•    Project Manager: Sandra Burtzos, 503-823-5594
•    Public Engagement: Ken Rumbaugh, 503-823-5131