Restoration Project Update (as of 12/4/2018)

For current construction updates and restoration information resources, please visit the Portland Parks & Recreation website

Keller Fountain: Project Update

Keller Fountain Park reopened November 19, 2018 after our contractor, Stacy & Witbeck, completed the planned Fall 2018 restoration work. More improvements to come in Phase 2 (Spring 2019).

 

Keller Fountain Park Construction:

  • Late June – Early August 2018
    • Phase 1 – Fountain concrete repairs (limited areas of park open)
  • September – November 2018
    • Phase 2 – Park and fountain restoration (park closed)
  • April – May 2019
    • Phase 3 – Finishing work (limited areas of park open)

Lovejoy Fountain Plaza: Project Update

Concrete pavement replacement, and electrical service modification required by PGE are complete. More improvements to come in Phase 2 (Spring 2019).

 

Lovejoy Fountain Park Construction:

  • July – October 2018
    • Phase 1 – Park and fountain restoration (park closed)
  • April – May 2019
    • Phase 2 – Finishing work (limited areas of park open)

Source Fountain

The Source Fountain mechanical work is completed, and the paving work is underway to install new bricks.  This fountain area should be reopened sometime during the first week of December. More improvements to come in Phase 2 (Spring 2019).

March – April 2019, Fountain restoration (fountain area closed)

Pettygrove Fountain Park

Improvements to come in Phase 2 (Spring 2019).

April – May 2019, Pettygrove Park – park restoration (park closed)